krikri
dotsforbanner.1a

INDUSTRIAL CONSTRUCTIONS

LOGISTICS

PROJECT OVERVIEW

KRI KRI

CLIENT

3 RD KM SERRES – DRAMA ROAD

LOCATION

FRIGO STAHL S.A.

DESIGN

FRIGO STAHL S.A.

PROJECT CONSTRUCTION

4 MONTHS

DURATION

KRI KRI

KRI KRI entrusted FRIGO STAHL S.A. with the construction of a new engine room and refrigeration installation. To that end, a housing area for a new cooling tunnel and a new engine room with a total area of 500m2 was constructed. An additional purpose of the new project was to reinforce and renovate the existing warehouse building to accommodate new production lines.

Project Highlights

  • Installation of 9 screw compressors and 2 evaporative condensers.

  • Installation of a new 1.250 KVA substation.

  • Reinforcement of the existing metal building.

  • Phased delivery for the installation of production equipment.

  • Complete refrigeration and electrical installation.

krikri