KONSTANTOPOULOS S.A. assigned us two simultaneous projects within its production facility. These were projects of different nature, carried out at the same time by an in-house technical team and with minimal disruption to the facility’s operation during the works. One project involved upgrading the wastewater treatment infrastructure, while the other involved converting existing storage areas into production facilities.

Key Project Highlights

  • Expansion of the biological wastewater treatment plant through the construction of 3 new tanks with a total capacity of 2,500 m³, integrated into the existing system

  • Modernization of 750+ m² of existing storage areas and conversion into functional production facilities