INDUSTRIAL CONSTRUCTIONS

LOGISTICS

PROJECT OVERVIEW

FALCON S.A.

CLIENT

KERATEA, ATTICA

LOCATION

FRIGO STAHL S.A.

DESIGN

FRIGO STAHL S.A.

PROJECT CONSTRUCTION

6 MONTHS

DURATION

FALCON S.A.

FALCON S.A. entrusted us with the construction of their new facilities, which include a storage building of 1.000 m2 with a height of up to 14m, featuring a composite mezzanine of 200 m2 for offices and a laboratory. Additionally, a loading area was constructed in the surrounding premises.

Project Highlights

  • Construction carried out on a particularly rocky terrain

  • Development on a very narrow plot with highly restricted access for construction machinery

  • Installation of fire-resistant panels on the roof and walls due to proximity to neighboring facilities

  • Construction of surrounding area infrastructure for loading small and large trucks (2 positions)