PROJECT CONSTRUCTION
8 MONTHS
DURATION
OLYMPOS
The dairy company OLYMPOS entrusted us with another complex project, requiring high technical precision and expertise. A central technological element of the project was the installation of a robotic pallet handling system, in collaboration with the specialized international firm STAHM LD. The project includes the construction of a new 1.800m2 freezing and storage building, an independent 800m2 building for chemical and spare parts storage and the development of a 5.000m2 surrounding area.Project Highlights
Construction of new refrigerated areas, fully ready to support the robotic warehouse.
Functional and structural integration of the new complex with the existing OLYMPOS factory.
The OLYMPOS factory remained fully operational throughout the construction period.