KONSTANTOPOULOS ΑΕ- OLYMP ΑΕ
CLIENT
3rd Km NATIONAL ROAD KATERINI-LARISSA, KATERINI
LOCATION
FRIGO STAHL S.A.
DESIGN
FRIGO STAHL S.A.
PROJECT CONSTRUCTION
7 MONTHS
DURATION
KONSTANTOPOULOS ΑΕ- OLYMP ΑΕ
“KONSTANTOPOULOS S.A.” entrusted FRIGO STAHL S.A. with the design and construction of an extension to its central warehouse at the olive processing plant, all while maintaining full operational capacity.
The 2,500m² expansion was planned and carried out in two phases to ensure seamless continuity of warehouse operations throughout the construction process.
Project Highlights
Excavation and foundations construction
Erection and cladding of the metal structure
Industrial flooring
Panel installation
Electromechanical & specialized installations (loading/unloading systems, fire protection, electrical works, etc.)