INDUSTRIAL CONSTRUCTIONS

LOGISTICS

PROJECT OVERVIEW

ISOMAT SA

CLIENT

AGIOS ATHANASIOS THESSALONIKI

LOCATION

FRIGO STAHL S.A.

CONSTRUCTION

11 ΜΗΝΕΣ

DURATION

ISOMAT SA

isomatWe have successfully completed ISOMAT’s new EPS production unit, the first in Greece with zero direct CO₂ emissions.
In less than 12 months, we delivered a 4,500m² facility fully aligned with sustainable development standards.

Our 10-year partnership with ISOMAT continues to thrive, contributing to the creation of innovative solutions for the future of industrial construction.

Project Highlights

  • Production and storage buildings for Materials Production with a total area exceeding 4,500m²

  • Landscaping and development of the surrounding area for storage and circulation, covering more than 12,000m²