PROJECT OVERVIEW
ARI
CLIENT
THESSALONIKI
LOCATION
FRIGO STAHL S.A.
DESIGN
FRIGO STAHL S.A.
ΚΑΤΑΣΚΕΥΗ ΜΕΛΕΤΗ
16 MONTHS
DURATION
ARI S.A.
Construction of an Industrial Building – Facilities for receiving, sorting and storing olives in ripening tanks, construction of a waste treatment facility, construction of a lagoon in the surrounding area, as well as a three-story office buildingProject Highlights
Construction of buildings with a total area of 13.300 m²
Three floors of offices 350 m²
Installation of 798 olive receiving tanks
Complete configuration of the surrounding area in a 27.300 m² field
Construction of a reservoir for the collection of liquid waste
Supply of underwater stainless steel sewage pumps and the supply and installation of a 90.000 liter stainless steel water tank
Supply and installation of a metal prefabricated water tank of 1.500 m3<sup></sup>
Construction of maturing tank bases
Construction of hydraulic solutions’networks (brine – soda – water), compressed air network and electrical drive installation
Steam network construction