Facilities receiving sorting storing olives
dotsforbanner.1a

INDUSTRIAL CONSTRUCTIONS

LOGISTICS

PROJECT OVERVIEW

ARI

CLIENT

THESSALONIKI

LOCATION

FRIGO STAHL S.A.

DESIGN

FRIGO STAHL S.A.

ΚΑΤΑΣΚΕΥΗ ΜΕΛΕΤΗ

16 MONTHS

DURATION

ARI S.A.

Construction of an Industrial Building – Facilities for receiving, sorting and storing olives in ripening tanks, construction of a waste treatment facility, construction of a lagoon in the surrounding area, as well as a three-story office building

Project Highlights

  • Construction of buildings with a total area of 13.300 m²

  • Three floors of offices 350 m²

  • Installation of 798 olive receiving tanks

  • Complete configuration of the surrounding area in a 27.300 m² field

  • Construction of a reservoir for the collection of liquid waste

  • Supply of underwater stainless steel sewage pumps and the supply and installation of a 90.000 liter stainless steel water tank

  • Supply and installation of a metal prefabricated water tank of 1.500 m3<sup></sup>

  • Construction of maturing tank bases

  • Construction of hydraulic solutions’networks (brine – soda – water), compressed air network and electrical drive installation

  • Steam network construction