construction of new building
dotsforbanner.1a

INDUSTRIAL CONSTRUCTIONS

LOGISTICS

PROJECT OVERVIEW

OLYMPOS

CLIENT

LARISSA

LOCATION

FRIGO STAHL S.A.

DESIGN

FRIGO STAHL S.A.

PROJECT CONSTRUCTION

6 MONTHS

DURATION

OLYMPOS

Expansion of existing facilities in Larissa through the construction of a new building including refrigeration and storage, office space, a chiller plant, and auxiliary areas with a total surface area of 8.900 m². The project includes innovative and automated robotic stretch wrapping and labelling machines.

Project Highlights

  • Working alongside a foreign firm supplying the automated logistics system

  • Compliance with strict international construction standards

  • Operation of unmanned laser guided vehicles (LGVs)

  • Fully automatic robot palletising system

  • Bespoke software design, tailored to the customer’s needs

  • Air coolers were “insulated coolers”